Construction work on ZIL station, the terminus of the Biryulyovskaya metro line, is more than a quarter complete. This was reported on the official website of the Mayor of Moscow.

“The overall construction readiness level of the station is 28%. Currently, the excavation work is completed and the installation of structures surrounding the manhole is complete. In addition, all utilities have been removed from the cul-de-sac construction area behind the station. Ongoing excavation work continues in the cul-de-sacs as part of the construction of the station complex – 26 thousand cubic meters have been developed here,” the announcement quoted Vladimir Efimov as saying, Deputy Mayor of Moscow for Urban Development Policy and Construction.
Experts turned to the construction of monolithic structures. They filled the podium tray and placed more than 10 thousand cubic meters. m concrete.
“In addition to the platform section with the possibility of transferring to the station of the same name on the Troitskaya line, the station complex is expected to create reversible dead ends for rolling stock, as well as a service line connecting to the Troitskaya metro line and ramp cameras,” said Maxim Gaman, General Director of JSC Mosinzhproekt.
ZIL station will become the terminus for the new radius and will ensure its integration into the capital's transport network. In particular, there will be transfers to the Trinity Line and Moscow Central Circle (MCC). Initially, trains will arrive here from the green line. The station is being built at the intersection of Likhachev Avenue with the street. The Ryabushinsky brothers near the MCC station platform of the same name. There will be two corridors with exits on both sides of Likhachev Avenue.